Client
Town of Claremont
Location
Claremont Aquatic Centre
Project Value
$600,000
Completed
December 2025
The situation
The Town of Claremont needed both changerooms at its aquatic centre fully refurbished before summer. The facility had to stay operational the entire time, when the male changeroom closed, the female had to remain open, and vice versa.
The scope was comprehensive: full demolition, waterproofing, epoxy flooring, new louvres and glazing, tiling, joinery, plumbing, electrical, exhaust fans, and painting.


The challenge
Two things defined this project.
One: sequencing. There was no window where both changerooms could close at once. The male side had to be completed and reopened before work on the female side could begin.
Two: quality control. Mid-project, slip resistance testing on the epoxy floor returned a result below the required P3/P4 rating. Both changerooms closed for two days while the floor was re-laid, retested, and signed off.
How we approached it
We staged the works so one changeroom was always available to the public. All progress communicated through scheduled meetings, regular email updates, and a Clarifications Register tracking every decision and approval.
When the floor issue emerged, we moved quickly, two days of closure, new floor laid, tested, and signed off. Non-conformance formally recorded, processes updated. The project finished on time and under budget, with both changerooms fully operational for the start of summer.

Our process
01
Secure
Pre-start planning, staging strategy locked in, and sequencing agreed with the Town before a single tool was lifted.
02
Deliver
Male changeroom completed first, to full specification, retested and signed off before female changeroom works began.
03
Work
Full refurbishment: demolition, waterproofing, epoxy floors, louvres, glazing, tiling, joinery, plumbing, electrical, painting.
04
Clean
Site kept safe and clean throughout. Public access to one changeroom maintained at all times during the works.
05
Handover
Delivered on time and under budget. Both changerooms fully operational for the start of summer. Final documentation provided at handover.