Welshpool Bus Depot: Workshop Bathroom, Lunchroom and Office Upgrade — Finished Three Weeks Early

Client

Programmed Facility Management

Location

Welshpool Bus Depot, Welshpool WA

Project Value

$72,993

Completed

February 2026

The situation

Welshpool Bus Depot needed its workshop bathroom, locker room, lunchroom and office upgraded. The spaces needed a fresher look and had to meet all current compliance requirements. The scope covered demolition of existing internal areas, floor preparation, epoxy and vinyl flooring, new internal doors and hardware, roller blinds, lockers, bench seating, tiled ceilings in the workshop and store office, electrical and plumbing amendments, tiling make-good, and painting.

The challenge

Welshpool is an extremely busy operational bus depot. The works had to happen around depot staff without disrupting daily operations. Safe access, clear communication and careful staging were essential.

When the existing vinyl flooring was lifted, moisture was identified on the substrate. A moisture test confirmed a moisture barrier would be required before the new flooring could go down.

How we approached it

We assessed the depot’s daily operations before starting so we understood how the spaces were used and where the pressure points were. Exclusion zones were set up with clear signage so depot staff knew where they could and couldn’t go. Both the client and on-site managers were kept informed throughout so everyone could plan around the works and communicate to their teams.

When the moisture issue was identified under the vinyl, it was flagged to the client immediately. A moisture test was carried out, a variation raised for the moisture barrier, and the additional scope was approved and incorporated without delay.

Through planning, flexibility and coordinated trade scheduling by Site Supervisor Steve Callahan, the project was completed in four weeks against a planned seven. Three weeks ahead of schedule, within budget, and the depot ran normally the whole time.

Our Process

01

Secure

Depot operations assessed before mobilisation. Exclusion zones and signage planned. Client and on-site managers briefed on the program and staging.

02

Deliver

Trades sequenced to minimise disruption. Proactive communication with all stakeholders kept the depot running normally throughout.

03

Work

Demolition, floor preparation, epoxy and vinyl flooring, moisture barrier installation, doors, lockers, bench seating, tiled ceilings, electrical, plumbing and painting.

04

Clean

Each area cleared and cleaned progressively. Work zones kept separate from depot operations at all times.

05

Handover

Completed three weeks ahead of schedule. Upgraded facilities fully operational and compliant.